Background

Solar Site View

For a century, the Sullivan mine was the largest lead mine in Canada and the main economic engine for Kimberley, BC. It ceased operation in 2001, leaving behind a huge industrial brownfield site and an industrial town with a need to reinvent itself.

Fortunately, Kimberley has another underdeveloped resource: one of the highest solar energy intensities in Canada. The “SunMine ™” – or “Mining the Sun ™” project was born out of the realization that the Sullivan brownfield with its heritage infrastructure, including roads, high-voltage transmission lines and sub-stations, could be used to take advantage of Kimberley’s solar energy potential. The sheer size of the land available (3,000 Ha) coupled with exceptional solar conditions (2,200 hrs per year) could make “SunMine” the largest solar farm in Canada.

OBJECTIVES

SunMine’s short-term objective is to develop a two (2) MW pilot photovoltaic (PV) plant on the brownfield site of the former Sullivan industrial compound in Kimberley, BC.
The feasibility of the project is based on a location that has exceptionally good conditions:

  1. one of the highest solar irradiation levels in Canada;
  2. A very large brownfield, owned by Teck, the former mining operator, that can be re-developed from a liability into an asset;
  3. Existing sub-stations connected to high capacity and under-utilized high voltage transmission lines

The goal is to achieve the lowest cost per Megawatt-hour, paving the way to grid parity and the development of an extensive high-performance solar farm.

 

Recent Posts

BC Hydro System Impact Study Completed

On May 22, 2013, BC Hydro completed the System Impact Study for the SunMine interconnection to the grid. The report concluded that the generation of electricity by the 2 MWp solar plant will have no negative impact on the grid.

Teck’s Stiles Sub-Station

SunMine will be connected to Teck’s owned Stiles sub-station, which is bar-connected to  BC Hydro’s  KBL sub-station and from there to three under-utilized 69 kV transmission line (T-line).   These exceptional circumstances could allow SunMine to significantly increase its capacity in the future without major modifications in the transmission system.

  1. Rezoning of SunMine Site Completed
  2. Environmental Assessment Completed
  3. EcoSmart completed SunMine’s feasibility study
  4. Engineering Review of Energy Model
  5. FAQ by the City of Kimberley
  6. Financial Information
  7. Teck Sustainability Report
  8. ICE Funding Announcement
  9. SunMine Test Announcement